PROJECTS

PBW - EMSF 2.png
PBW - EMSF 3.png
PBW - EMSF 1.png
Crosslinx, Toronto
Eglinton Maintenance & Storage Facility
Year: 2016-2020
Value: Over $250 Million
  • Installation of 27.6 kV distribution and temporary power over entire facility
  • Installation of transformer, switchgear, and generator pads
  • Installation of 340 Overhead Catenary System (OCS) concrete bases
  • Installation of over 500,000 feet of 4" duct bank for dry utilities
  • Installation of over 200 cable vaults
60 Bloor Street - 2.png
60 Bloor Street - 3.png
60 Bloor Street - 1.png
60 Bloor Street West, Toronto
Performance Optimization &  Wall Clad
Year: 2018 - 2019
Value: Over $10 Million
  • Retrofit of the perimeter induction unit system (75 per floor)
  • Installation of 4 new boilers, pumps, 2 humidifiers, fuel oil line, meters, VFD's, fan motors
  • Replacement of supply fan coils
  • New hot water system throughout the 16-floor building
  • Controls, insulations, mechanical wiring, and TAB
PBW - Square One Target Backfill3.png
PBW - Square One Target Backfill2.png
PBW - Square One Target Backfill1.png
Square One Shopping Centre, Mississauga
Target Backfill (Redemise)
Year: 2018 - 2019
Value: Over $6 Million
  • Installation of 27.6 kV and 13.8 kV switchgear, metering cabinets, and S&C Vistagear
  • Installation of temporary and permanent HV cable trays
  • Installation of new duct banks + overhead feeds for new distribution configurations
  • Demolition of old equipment + replacement with new equipment
  • Hook-up of temporary 2000W generator for operation of retail spaces for larger shutdown
CCIW Lab Modernization - 3.png
CCIW Lab Modernization - 2.png
CCIW%20Lab%20Modernization%20-%204_edite
CCIW Laboratory, Burlington
Modernization Project
Year: 2018 - 2019
Value: Over $3 Million
  • One of the world's leading water research centers.
  • CCIW LMP consisted in a phased renovation of laboratory facilities, office facilities, and life safety systems.
  • The project was phased strategically to ensure the facility remained operational at all times.
  • HVAC
  • Plumbing
PBW - Amazon 2.png
PBW - Amazon 3.png
PBW - Amazon 1.png
Amazon, Bolton
Fulfillment Centre - Distribution
Year: 2018-2019
Value: Over $3 Million
  • Installation of 44 kV switchgear, transformers, and terminal poles
  • (1x) 4MVA transformer + (2x) 3 MVA transformers
  • 2,300 feet of concrete encased, steel reinforced, duct bank
  • Frost free foundations for all equipment
PBW - ERMF 2.png
PBW - ERMF 3.png
PBW - ERMF 1.png
Metrolinx, Whitby
East Rail Maintenance Facility (ERMF)
Year: 2015-2017
Value: Over $300 Million
  • HIGH VOLTAGE
  • Design-build of 44 kV power distribution
  • Durham's largest 44 kV substation at time of installation at 25 MVA!
  • Installation of transformers, switchgear, generator pads
  • Installation of 400 Overhead Catenary System (OCS) concrete bases
  • Installation of over 700,000 feet of 4" duct bank for dry utilities
  • Installation of over 200 manholes
East Rail Maintenance Facility - 2.png
PBW - ERMF 1.png
East Rail Maintenance Facility - 3.jpg
Metrolinx, Whitby
East Rail Maintenance Facility (ERMF)
Year: 2015-2017
Value: Over $300 Million
  • MECHANICAL
  • DBFM delivery
  • Plumbing and Drainage
  • HVAC
  • Underground mechanical building systems
  • Single point service connections
  • Mechanical concept, design, and isntallation
  • Specialized exhaust systems
  • Specialized hume hood exhausts
  • BIM modelling of our own work
PBW - YYZ 3.png
PBW - YYZ 2.png
PBW - YYZ 1.png
YYZ Airport, Mississauga
Air Canada Substation & Duct Bank Repl.
Year: 2016
Value: Over $6 Million
  • Installation of (3x) 13.8 kV transformers
  • Installation of 5-Bay and 6-Bay 13.8 kV switchgear line-ups
  • Preparation of all foundations for line-up of 27.6 kV switchgear for Alectra utilities incoming feeder
  • Duct bank, manholes, and slab foundations for (2x) transformers
  • All cabling, temporary feeders, and demolition of old equipment
PBW - Square One South Expansion 2.png
PBW - Square One South Expansion 3.png
PBW - Square One South Expansion 1.png
Square One Shopping Centre, Mississauga
South Expansion - HV Equipment Repl.
Year: 2014 - 2016
Value: Over $8 Million
  • 13.8 kV installations in Substations #1, #2, #3
  • 13.8 kV installations in HV Rooms #1, #2
  • 13.8 kV installations in ER Substation
  • Demolition of old equipment + repalcement with new equipment
  • Installation of 600 amp, 15 kV cable bus system, metering cabinets, and SCADA rack
  • Installation of new duct banks on City Centre Drive, Square One Drive, and Truck Tunnel
222%20Jarvis%20Street%20-%202_edited.jpg
222%20Jarvis%20Street%20-%203_edited.jpg
222 Jarvis Street - 1.png
222 Jarvis Street, Toronto
Retrofit and Modernization
Year: 2012-2014
Value: Over $10 Million
  • Phase 1: Remediation and base building restoration of 445,000 square feet
  • Phase 2: Completion of tenant work
  • Retrofit major building systems: building envelope upgrades, insulation, and glazing
  • Vertical transportation upgraded and all mechanical systems replaced and brought up to code
  • New electrical services provided for retrofit
  • HVAC
  • Plumbing & Drainage,
  • Heat Recovery Systems,
  • Thermal Insulation
CN Tower Observation Deck - 1.png
CN Tower Observation Deck - 2.png
CN Tower Observation Deck - 3.jpg
CN Tower, Toronto
Observation Deck Renovation
Year: 2018
Value: Over $3 Million
  • Renovation of the third floor
  • HVAC
  • Plumbing/Piping
  • Thermal Insulation
  • Controls
  • Air Balancing
  • Fire Protection
  • Duct Cleaning
  • Phasing Included
Corus Quay - 4.jpg
Corus Quay - 3.jpg
Corus Quay - 1.jpg
Corus Quay, Toronto
Originally named "First Waterfront Place"
Year: 2007-2010
Value: Over $150 Million
  • Eight storey commercial office tower located on a 2.5 acre waterfront site. It was the first major development planned for the East Bayfront Precinct
  • LEED Gold Certified under Core and Shell
  • Full mechanical services provided
  • HVAC
  • Controls
  • Plumbing
  • Coordination with unique site conditions